Woodland Generation Station Unit 2

CLIENT: Modesto Irrigation District
LOCATION: Modesto, CA

The Modesto Irrigation District (MID) originally retained IEC to provide project management and construction management services for the development and construction of a new 80 MW gas turbine generating facility owned and operated by MID.

Due to IEC’s responsiveness and quality of work, the contract expanded from $150,000 to $900,000 to perform design reviews, provide construction management, prepare a complete engineering and construction schedule, develop a detailed budget schedule, provide full-service construction management and oversee additional management services for the Owner.

The project was successfully installed, completed, and providing power in 2003. The plant consists of a 47 MW GE LM6000 Sprint combustion turbine generator in combined cycle with a single 37 MW steam turbine generator. A stateof-the-art, customized duct-fired heat recovery steam generator allows the plant to produce 80 MW net power at full-load condition. The plant also includes the Mark VI Control System, 2000-Ton Chiller, SCR and CO Emissions Systems and Cooling Tower. Designated the Woodland Generating Station Unit 2, the new power plant was constructed on the site of the existing MID Woodland Generating Station.

The client was extremely pleased with our responsiveness and quality of performance and contracted with IEC to completely manage their next project.